NHPC strives to sustain progress at Teesta Low Dam-III HEP

 NHPC is pulling out all stops to ensure that erection of radial gate for bay-6 proceeds smoothly once these hydro mechanical (HM) works are taken up in November 2011.

 

The radial gate is critical for timely commissioning of its 132 MW Teesta Low Dam stage-III hydro electric project.
The rest of the HM works at the site are progressing as per schedule, with erection of radial gates already completed in bays 4, 5 and 7 and that for bay-3 progressing swiftly. However, the concreting works at barrage bays 1 and 2, out of a total of 7 bays, are yet to be completed.

At the power house works' front, NHPC lagged behind schedule for all targets set for the month of September, a complete opposite of the situation during August 2011 wherein all targets were surpassed.

With a scheduled plan to achieve 179 cum and 600 cum of concreting in PH and TRC floor respectively, NHPC has completed only 25 cum and 405 cum of concreting during the month.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!