Unresolved contractual issues hamper progress of Parbati-II HEP works

Unresolved contractual issues hamper progress of Parbati-II HEP works

The pending resolution of contractual issues has led to severe time and cost overruns for completion of work related to the head race tunnel (HRT) and other critical activities at NHPC's Parbati-II hydro electric project (HEP). More delays are now expected since no solution seems to be in sight, despite numerous negotiations held between the state-owned equipment major, BHEL and NHPC. No progress on HRT overt lining works in August has forced NHPC to carry forward the balance quantity to be finished in the coming month. Barely half of the lining has been laid out during the month, with 16,012 m of overt lining still remaining to be completed for the project. Moreover, 4,915 m of HRT needs to be excavated as per schedule to avoid any further delay in project commissioning. Also, in the sphere of electro mechanical (E&M) works, the power house (PH) activities were suspended due to slide of backhill slope. Although the work has resumed, the progress is not up to the mark for the project. In contrast to this, the retendering of Manihar Pancha and Jiwa Nallah feeder tunnels has progressed smoothly. With the excavation done so far, 59 m and 1291 m for the two tunnels respectively, remains to be completed. Parbati-II HEP, in the state of Himachal Pradesh, entails the construction of a 85 m high, concrete gravity dam, a 6 m x 31.52 km Head Race Tunnel, a 17 m x 130 m surge shaft, 2 m x 3.5m x 2133 m pilot shaft, a surface power house, pelton turbine and a 400 kV switchyard.  

NTPC gains on commencement of 500 Mw thermal power project

State owned power generator National Thermal Power Corporation (NTPC) is trading higher by more than 2 per cent at Rs 168 after commencement of 500 Mw thermal power project. “The Unit 3 of 500 Mw of Simhadri super thermal power project is declared on commercial operation w.e.f. 00:00 hours of September 16, 2011,” the state-owned power company said in a filing to the stock exchanges. “With this the commercial capacity of Simhadri is 1500 Mw and that of NTPC is 30,330 Mw,” it added.

Coal supply disruption forces NTPC to cut down generation

Generation at the 2,600-Mw NTPC’s Ramagundam Thermal Power Station further declined to 1,400 Mw due to disruption in coal supplies from Singareni coalfields, impacting power supply across the Southern grid.

Rise in fuel prices pushes PSPCL's power purchase cost for Q1 FY12

Change in the fuel cost of central generating stations operated by NTPC and National Power Corporation (NPC) has led to an increase in the power purchase cost (PPC) of Punjab State Power Corporation Limited (PSPCL) for the first quarter (Q1) of the ongoing fiscal.

Gujarat gets $100M ADB loan for solar power facilities

Asian Development Bank has granted a $100 million loan to the Indian state of Gujarat to support acceleration of work at new large-scale solar power facilities.

Lauren Jyoti wins contract to build Indian solar plant

Godawari Green Energy has awarded a Rs5.51bn or $115.1 million contract to Lauren Jyoti to build a 50MW solar thermal power plant in Rajasthan, India.

CIL subsidiaries to supply coal to seven projects

Coal India Limited has called for supply of coal to power stations for meeting their input requirement.

Bangladesh-India cross-border electricity trade to be delayed further

The Bangladesh-India cross border electricity trade is set to be delayed as the power purchase deal was not inked during the Indian Prime Minister Manmohan Singh’s visit to Bangladesh.

India's Power Grid awards enterprise solutions contract to ZTE

ZTE Corporation bagged a contract from Power Grid Corporation of India to help the state-run firm reduce costs.

Pakistan, Iran to expedite gas, power projects

Pakistan Prime Minister Yousuf Raza Gilani has agreed with Iranian President Mehmoud Ahmadinejad to expedite  the import of 1000MW electricity from Iran.

NHPC on track for timely commissioning of 132 MW Teesta HEP

NHPC is ensuring that erection of radial gate for bay-6 proceeds smoothly for a timely commissioning of its 132 MW Teesta Low Dam stage-III hydro electric project.

Madhya Pradesh MW super critical TPP on speedy development route

 Unit-1 of the 2x660 MW super critical coal based plant in the state of Madhya Pradesh has made substantial progress towards achieving its major milestones.

Maharashtra ends zero cross subsidy surcharge

The Maharashtra Electricity Regulatory Commission has ended the zero cross subsidy surcharge regime it introduced in 2006 for open access consumers.

Techno's Simran first to cross 100MW under renewable energy scheme

This brings India closer to its target of 15% capacity addition through renewable energy by the year 2020.

First Solar to supply 100MW solar modules to Reliance Power

First Solar has signed an agreement with Reliance Power (RP) to supply 100MW of solar modules for its project in Rajasthan, India.

Indowind procures wind turbines from Shanghai Electric

Indowind Energy is buying fourteen 2MW turbines from Shanghai Electric Group for its next project.  

AERB makes recommendations for India's nuclear plants

The Atomic Energy Regulatory Board has come up with a set of recommendations for safety of nuclear power plants in India.