, India

NHPC to press joint venture to fulfill contract

 

NHPC will ensure that HJV fulfill its role as the leader of the consortium for LOT PB-2 project. It also wants to impose liquidated damages for the latter’s shoddy performance.


Himachal Joint Venture was constituted by Maytas Infra Limited, Sri Shakaranarayana Construction Company and Nagarjuna Construction Company to successfully bid for fourth head race tunnel of the project contract, dubbed LOT PB-2.


HJV is nowhere to be found at the project and left SSCC is working under power of attorney granted by the other two constituents.


The National Hydroelectric Power Corporation is free to terminate the contract but this move would be fraught with difficulties and time consuming. The delay cause additional interest to accrue on the amount already spent on the project, along with further cost escalation due to increase in time. The per-unit rate charged for excavation by the new contractor would also be higher, because new equipment has to be deployed for the balance work.


It would also be very difficult to find contractors interested in taking up the uncompleted works of another contractor.

Follow the link for more news on

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!