NHPC to press joint venture to fulfill contract

 

NHPC will ensure that HJV fulfill its role as the leader of the consortium for LOT PB-2 project. It also wants to impose liquidated damages for the latter’s shoddy performance.


Himachal Joint Venture was constituted by Maytas Infra Limited, Sri Shakaranarayana Construction Company and Nagarjuna Construction Company to successfully bid for fourth head race tunnel of the project contract, dubbed LOT PB-2.


HJV is nowhere to be found at the project and left SSCC is working under power of attorney granted by the other two constituents.


The National Hydroelectric Power Corporation is free to terminate the contract but this move would be fraught with difficulties and time consuming. The delay cause additional interest to accrue on the amount already spent on the project, along with further cost escalation due to increase in time. The per-unit rate charged for excavation by the new contractor would also be higher, because new equipment has to be deployed for the balance work.


It would also be very difficult to find contractors interested in taking up the uncompleted works of another contractor.

Follow the link for more news on

Jaringan listrik lemah Vietnam menghambat kebijakan pembelian listrik yang langsung

Infrastruktur energi yang buruk menghambat integrasi kapasitas baru dari proyek energi terbarukan (EBT).

Penutupan pembangkit listrik batu bara baru di ASEAN pada 2040 mungkin tercapai

Penambahan pembangkit batu bara baru dan retrofit pembangkit yang ada menjadi risiko lebih besar dalam transisi.

ADB menyetujui pinjaman senilai $500 juta untuk mendukung transisi energi Indonesia

Ini bertujuan membangun kerangka kebijakan yang kokoh dalam mendukung peralihan menuju energi bersih.

Avaada meningkatkan beban energi terbarukan untuk penuhi permintaan pusat data India

Perusahaan menargetkan kapasitas energi terbarukan sebesar 30 gigawatt pada 2030.

Asia-Pasifik mungkin tidak mencapai target energi terbarukan

Negara-negara di kawasan itu harus menarik investasi untuk memajukan tujuan energi bersih mereka.

Laba bersih Adaro turun 12% menjadi $880 juta di Semester 1

Pendapatan turun 15% menjadi $2,97 miliar pada periode tersebut.

ACEN dan Barito Renewables bermitra untuk mempercepat energi angin di Indonesia

Kemitraan ini akan dijalankan oleh anak perusahaan mereka.

Malaysia diminta mengintegrasikan jaringan listrik untuk mempercepat pertumbuhan tenaga surya

Pembatasan penetrasi tenaga surya ke jaringan pada 24% dari permintaan puncak dapat menghambat ekspansi.