Reliance's 1,200MW Rosa TPP to shut due to coal shortage

Reliance Power`s 1,200 MW Rosa Thermal Power Plant is faced with serious coal supply disruptions that it may be forced to shut down the plant.

 

The company has asked the coal ministry to restore coal supply so that a forced shut down may be avoided.

The coal is sourced from the Ashoka coalfields of Central Coalfields Ltd. S

The company contends that only one rake of domestic coal was dispatched by CCL for the month of March, till March 15, 2012, even though the stipulated allocation for the TPP is 53 rakes per month.

Prolonged coal shortages have also meant that the thermal power plant is now left with only 12 hours worth of stock.

Millions of people in the state of Uttar Pradesh stand to get affected unless coal supply to the plants restored.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!