THDC ascertains responsibility for project's time and cost overrun

Tehri Hydro Development Corporation held its second meeting to determine responsibility for time and cost overrun in its 400 MW Koteshwar hydro electric project in Uttarakhand.

 

Marred with both time and cost overruns, the project's revised cost estimates as of June 2009 stand at Rs 2,288.59 crore, as against Rs 1,301.56 crore at October 1999 price levels.

The hydel major was also able to synchronize the first unit of the project only this month when it was expected to go on stream in December 2010.

The second unit is expected to begin commercial operations by June 2011. The third and the fourth units are expected to go on stream in February and March 2012, respectively.

Follow the link for more news on

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!