NHPC's Uri-II hydro project on track for December commissioning

NHPC has completed dam excavation and concreting for its 240 MW Uri-II hydroelectric project in June with all four unit on track for commissioning by December 2011.

 

Each unit has a capacity of 60 MW. 

The Uri HEP has also made significant progress in overt and invert lining associated with head-race-tunel works. The lining is nearing completion for junction points and D/s Adit-III. In addition to this, TRT excavation and power house concreting was completed during the month.

Trial run of spillway radial gates 1, 2 and 3 was successfully conducted, following which erection of SRG 4 has begun. Erection of trash rack of head regulator gates and HRT intake gates has concluded whereas boxing up of unit 3 is progressing sequentially. Furthermore, the coffer dam was restored and work on critical activities such as radial gates and civil works was restarted in beginning of June.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!