India assures six transmission projects completed by year end despite facing delays

The delay was caused by the Supreme Court judgement on transmission lines.

The Ministry of Power has clarified that only six transmission projects of the Power Grid Corporation of India Limited (PGCIL) with a total value of $792.7m (INR6,500 crore) faced hurdles due to Supreme Court judgement on transmission lines in Great Indian Bustard areas. With issues already addressed, these are on track to be completed by end-2024, it noted.

Authorities issued the statement following reports that said 18 of 50 projects of the PGCIL face an average of 32-month delay.

The ministry said no new generation capacity is hindered by delays in the PGCIL transmission projects. All projects implemented in the past five years were completed before generation commenced, it added.

“The transmission schemes are planned keeping in view the demand scenario in future and lines may not be loaded to their full capacity from the year of commissioning.  Interim arrangements are also made, as required, for evacuation of power, till the final transmission system is ready,” the ministry said. 

India said it is targeting to complete the high-voltage alternating current transmission system within 24-36 months and the high-voltage direct current system within five years. This is less than the implementation of transmission projects in other countries that go beyond eight to nine years, it noted. 

$1 =  INR82 

Follow the link for more news on

Jaringan listrik lemah Vietnam menghambat kebijakan pembelian listrik yang langsung

Infrastruktur energi yang buruk menghambat integrasi kapasitas baru dari proyek energi terbarukan (EBT).

Penutupan pembangkit listrik batu bara baru di ASEAN pada 2040 mungkin tercapai

Penambahan pembangkit batu bara baru dan retrofit pembangkit yang ada menjadi risiko lebih besar dalam transisi.

ADB menyetujui pinjaman senilai $500 juta untuk mendukung transisi energi Indonesia

Ini bertujuan membangun kerangka kebijakan yang kokoh dalam mendukung peralihan menuju energi bersih.

Avaada meningkatkan beban energi terbarukan untuk penuhi permintaan pusat data India

Perusahaan menargetkan kapasitas energi terbarukan sebesar 30 gigawatt pada 2030.

Asia-Pasifik mungkin tidak mencapai target energi terbarukan

Negara-negara di kawasan itu harus menarik investasi untuk memajukan tujuan energi bersih mereka.

Laba bersih Adaro turun 12% menjadi $880 juta di Semester 1

Pendapatan turun 15% menjadi $2,97 miliar pada periode tersebut.

ACEN dan Barito Renewables bermitra untuk mempercepat energi angin di Indonesia

Kemitraan ini akan dijalankan oleh anak perusahaan mereka.

Malaysia diminta mengintegrasikan jaringan listrik untuk mempercepat pertumbuhan tenaga surya

Pembatasan penetrasi tenaga surya ke jaringan pada 24% dari permintaan puncak dapat menghambat ekspansi.