Indonesia expedites massive coal-fired power project

The Indonesian government has set an October deadline for the coal-fired power plant project in Central Java.

The $4 billion power plant, the largest of its kind in Southeast Asia, has been delayed for months due to land acquisition issue, as well as the district government’s refusal to issue a permit allowing the project contractor to bring the necessary equipment and machinery to the construction site.

Hatta Rajasa, the coordinating minister for the economy, announced the establishment of a task force to monitor the construction of the 2x1000-megawatt coal-fired power plant. Hatta made the announcement after meeting with related ministries, local government officials and executives from state-utility firm Perusahaan Listrik Negara.

“It must be done by October,” Hatta said.

Hatta said that the task force will consist of relevant stakeholders, while representatives from the Attorney General’s Office will also join to act as a legal watchdogs for the states, as some issues involve state administration law, the minister said.

One key duty of the task force will be to supervise the access permit, Hatta said.

Adaro Energy, an unit of Indonesia’s second-largest coal miner Adaro, joined Japanese firms Electric Power Development (J-Power) and Itochu to develop the 2,000 MW plant. The initial completion date for the power plant was 2016.

Nur Pamudji, PLN’s president director, said that the power plant will commence operations in 2017, meaning the project has been delayed by about a year.

For more.

Jaringan listrik lemah Vietnam menghambat kebijakan pembelian listrik yang langsung

Infrastruktur energi yang buruk menghambat integrasi kapasitas baru dari proyek energi terbarukan (EBT).

Penutupan pembangkit listrik batu bara baru di ASEAN pada 2040 mungkin tercapai

Penambahan pembangkit batu bara baru dan retrofit pembangkit yang ada menjadi risiko lebih besar dalam transisi.

ADB menyetujui pinjaman senilai $500 juta untuk mendukung transisi energi Indonesia

Ini bertujuan membangun kerangka kebijakan yang kokoh dalam mendukung peralihan menuju energi bersih.

Avaada meningkatkan beban energi terbarukan untuk penuhi permintaan pusat data India

Perusahaan menargetkan kapasitas energi terbarukan sebesar 30 gigawatt pada 2030.

Asia-Pasifik mungkin tidak mencapai target energi terbarukan

Negara-negara di kawasan itu harus menarik investasi untuk memajukan tujuan energi bersih mereka.

Laba bersih Adaro turun 12% menjadi $880 juta di Semester 1

Pendapatan turun 15% menjadi $2,97 miliar pada periode tersebut.

ACEN dan Barito Renewables bermitra untuk mempercepat energi angin di Indonesia

Kemitraan ini akan dijalankan oleh anak perusahaan mereka.

Malaysia diminta mengintegrasikan jaringan listrik untuk mempercepat pertumbuhan tenaga surya

Pembatasan penetrasi tenaga surya ke jaringan pada 24% dari permintaan puncak dapat menghambat ekspansi.