, India

PEPCO exec urges for Guddu project’s timely completion

PEPCO’s managing director urged for the completion of the Guddu Power Project within the stipulated period or earlier.

The period is 30 months for the open cycle and 36 months for the combined cycle.

Mr Tahir Basharat Cheema Managing Director Pakistan Electric Power Company said that one of the causes of the present energy crisis in Pakistan is delay in completion of ongoing power projects.

He however noted that M/s Harbin Power Engineering Company, one of the three largest Chinese Companies manufacturing power plants, has the experience and expertise to complete the additional 747 MW combined cycle power plant at Guddu Thermal Power Station with the stipulated period. The proposed power project would comprise a 747 MW combined cycle power plant consisting of two gas turbines of 243MW each, two heat recovery steam generators followed by one steam turbine  having a capacity of 261 MW and associated equipment.

Cheema said that the energy policy of present government envisages that increase in power generation should be made in tandem with the objective of producing energy at affordable cost. The 747 MW Combined Cycle Guddu Power Project is therefore of great significance, as it is not only  one of the biggest thermal projects in the country fueled by gas, but would also produce affordable energy.

He added that the key to success is good and professional management of the project. He urged Mr Yang Qingly to hold regular meetings with officials of PEPCO and other related departments so that hurdles or delays that may come in the way of the project during its execution are removed well in advance. These interactions he said would help mitigate the issues that may pop up. “This project has to be a success story in Pakistan” he emphasized.

The contract for 747 MW Combined Cycle Power Project Guddu was signed on 19 September 2009 with M/s Harbin Power Engineering Company and General Electric USA having a capacity of 747 MW, with an estimated cost of Pak Rs 59,775.41 million and is schedule to be completed within 36 months. 85 percent of the project has already been financed by China Exim Bank and US Exim Bank while the balance would be financed by the Government of Pakistan.

Follow the link for more news on

Jaringan listrik lemah Vietnam menghambat kebijakan pembelian listrik yang langsung

Infrastruktur energi yang buruk menghambat integrasi kapasitas baru dari proyek energi terbarukan (EBT).

Penutupan pembangkit listrik batu bara baru di ASEAN pada 2040 mungkin tercapai

Penambahan pembangkit batu bara baru dan retrofit pembangkit yang ada menjadi risiko lebih besar dalam transisi.

ADB menyetujui pinjaman senilai $500 juta untuk mendukung transisi energi Indonesia

Ini bertujuan membangun kerangka kebijakan yang kokoh dalam mendukung peralihan menuju energi bersih.

Avaada meningkatkan beban energi terbarukan untuk penuhi permintaan pusat data India

Perusahaan menargetkan kapasitas energi terbarukan sebesar 30 gigawatt pada 2030.

Asia-Pasifik mungkin tidak mencapai target energi terbarukan

Negara-negara di kawasan itu harus menarik investasi untuk memajukan tujuan energi bersih mereka.

Laba bersih Adaro turun 12% menjadi $880 juta di Semester 1

Pendapatan turun 15% menjadi $2,97 miliar pada periode tersebut.

ACEN dan Barito Renewables bermitra untuk mempercepat energi angin di Indonesia

Kemitraan ini akan dijalankan oleh anak perusahaan mereka.

Malaysia diminta mengintegrasikan jaringan listrik untuk mempercepat pertumbuhan tenaga surya

Pembatasan penetrasi tenaga surya ke jaringan pada 24% dari permintaan puncak dapat menghambat ekspansi.