Gas-coal power plant in Timika to be realized soon

The gas and coal power plant project in Timika will commence this year.

 

It has so far been delayed for five years.

Manager of state power firm said that PLN was already allowed to  move the machinery of PLTGB from Labuan Bajo to Timika.

The 2x3 megawatts PLTGB machinery which had been imported from Germany was originally meant to increase the power capacity in Manggarai Barat regency, East Nusa Tenggara.

Farwas said PLN has received a Decision of Mimika Regent on the granting of land as a location for building the PLTGB in Ayuka hamlet, which was a port for explosives of PT Freeport Indonesia which had been granted to the Mimika regency administration.

State Enterprises Minister Dahlan Iskan when he was President Director of state oil company PT Pertamina had made an inspection of the location of the future Timika PLTGB in Ayuka hamlet in mid-2011.

Farwas said that if the project could be realized in a not too distant future, in the next three to five years, the people of Timika would always have electricity.

 

https://www.antaranews.com/en/news/81928/pltgb-project-in-timika-to-be-realized-soon

Jaringan listrik lemah Vietnam menghambat kebijakan pembelian listrik yang langsung

Infrastruktur energi yang buruk menghambat integrasi kapasitas baru dari proyek energi terbarukan (EBT).

Penutupan pembangkit listrik batu bara baru di ASEAN pada 2040 mungkin tercapai

Penambahan pembangkit batu bara baru dan retrofit pembangkit yang ada menjadi risiko lebih besar dalam transisi.

ADB menyetujui pinjaman senilai $500 juta untuk mendukung transisi energi Indonesia

Ini bertujuan membangun kerangka kebijakan yang kokoh dalam mendukung peralihan menuju energi bersih.

Avaada meningkatkan beban energi terbarukan untuk penuhi permintaan pusat data India

Perusahaan menargetkan kapasitas energi terbarukan sebesar 30 gigawatt pada 2030.

Asia-Pasifik mungkin tidak mencapai target energi terbarukan

Negara-negara di kawasan itu harus menarik investasi untuk memajukan tujuan energi bersih mereka.

Laba bersih Adaro turun 12% menjadi $880 juta di Semester 1

Pendapatan turun 15% menjadi $2,97 miliar pada periode tersebut.

ACEN dan Barito Renewables bermitra untuk mempercepat energi angin di Indonesia

Kemitraan ini akan dijalankan oleh anak perusahaan mereka.

Malaysia diminta mengintegrasikan jaringan listrik untuk mempercepat pertumbuhan tenaga surya

Pembatasan penetrasi tenaga surya ke jaringan pada 24% dari permintaan puncak dapat menghambat ekspansi.