Adani Power eyes conclusion of critical works of unit-1 Tiroda thermal plant

Adani Power Limited will wrap up all the critical activities of the 660 MW unit-I of the Tiroda Thermal Power Plant by January next year.

 

They have revised the commissioning schedule of the project twice during the ongoing fiscal year.

The insulation and refractory works associated with the steam generator works are progressing steadily along with the turbine generator activities, including piping and evacuation, which are well under way.

The cooling tower is already in the process of being commissioned and coal or ash handling system is being erected. The coal firing process, which was forced to be delayed by a period of 5 months, is expected to be concluded by the end of December.

The project, which initially had a capacity of 2x660 MW, is now being expanded to 3,300 MW with 3 more units of 660 MW each being implemented in the second phase. The TPP was expected to meet most of its coal requirement from captive mines, though it was awarded two coal blocks with combined estimated reserves of approximately 170 MT.

Follow the link for more news on

Jaringan listrik lemah Vietnam menghambat kebijakan pembelian listrik yang langsung

Infrastruktur energi yang buruk menghambat integrasi kapasitas baru dari proyek energi terbarukan (EBT).

Penutupan pembangkit listrik batu bara baru di ASEAN pada 2040 mungkin tercapai

Penambahan pembangkit batu bara baru dan retrofit pembangkit yang ada menjadi risiko lebih besar dalam transisi.

ADB menyetujui pinjaman senilai $500 juta untuk mendukung transisi energi Indonesia

Ini bertujuan membangun kerangka kebijakan yang kokoh dalam mendukung peralihan menuju energi bersih.

Avaada meningkatkan beban energi terbarukan untuk penuhi permintaan pusat data India

Perusahaan menargetkan kapasitas energi terbarukan sebesar 30 gigawatt pada 2030.

Asia-Pasifik mungkin tidak mencapai target energi terbarukan

Negara-negara di kawasan itu harus menarik investasi untuk memajukan tujuan energi bersih mereka.

Laba bersih Adaro turun 12% menjadi $880 juta di Semester 1

Pendapatan turun 15% menjadi $2,97 miliar pada periode tersebut.

ACEN dan Barito Renewables bermitra untuk mempercepat energi angin di Indonesia

Kemitraan ini akan dijalankan oleh anak perusahaan mereka.

Malaysia diminta mengintegrasikan jaringan listrik untuk mempercepat pertumbuhan tenaga surya

Pembatasan penetrasi tenaga surya ke jaringan pada 24% dari permintaan puncak dapat menghambat ekspansi.