, Malaysia

GE moving fast to repower Japan post Tsunami

The lights are coming back on in Tokyo, thanks in part to the extremely fast installation of GE gas turbines which are plugging the energy gap left by the closure of the Fukishima nuclear plant.

Speaking at a PowerGen Asia press event to announced a strategic MOU with Toshiba which will see the latter use GE Gas turbines in its combined cycle plants in Japan and beyond, GE’s CEO and President of Thermal Products Paul F. Browning outlined how the US giant had pulled out all the stops to get gas turbines up and running quickly to meet the energy demand.

In the day following the Japanese Tsunami, says Browning, the GE Team met to discuss ways they could get Japan repowered quickly. The first solution was to suggest using jet engines usually seen in the aerospace division . But by installing and connecting ten of GE’s LM2500 units, which together could produce 250MW or enough for a small power plant, GE was able to deliver new power with 90 days of the Tsunami. These engines were originally designed to power wide bodied aircraft such as the Boeing 707 but havd a new lease of life as aero-derivitives. A lot of these are installed in remote locations such as mines in Ausrralia and LNG plants. In Japan they were loaded onto soviet transorters known as Antonov’s and flown to Japan. Less romantically, some came by ship.
 

Just a few months after that the company also delivered and installed a 6FA 120 MW unit. As a follow up, the heavier turbines, which are marketed for untilities by GE’s Thermal Products group moved in and will have installed a further two 9FA gas turbines which can produce 250 MW each just in time for peak summer demand next year.
Normally this process would take at least 2 years, but Browning says GE will have it done within 17 months. Going forward he sees a lot of potential for the company’s new “FlexEffeciencey” 250 MW units known as GE Frame 9FB Gas Turbines. It is these the company is hoping to sell in big numbers in Japan and beyond through its non-exclusive tie up with Toshiba. So what’s the big differnece between these new units and the older ones ?
 

According to Browing the new engines are 61 % efficient as part of a combined cycle plant which is 1.5 % better than anything GE has offereed before. “The other big difference is the time to start – we can start it in 28 minutes compared to 50 minutes previously, and we can ramp at 51MW per minute – previously 35MW per minute –a 50 % increase, and we can turn down the plant to 40 % of full load and previously that was 50 % f full load. All of those are industry leading numbers. “
 

Browing adds that this brings the total of 9FB.05 engines to 5 units – 2 in China with Harbin Electric and 2 in Japan with Toshiba

Follow the link for more news on

Jaringan listrik lemah Vietnam menghambat kebijakan pembelian listrik yang langsung

Infrastruktur energi yang buruk menghambat integrasi kapasitas baru dari proyek energi terbarukan (EBT).

Penutupan pembangkit listrik batu bara baru di ASEAN pada 2040 mungkin tercapai

Penambahan pembangkit batu bara baru dan retrofit pembangkit yang ada menjadi risiko lebih besar dalam transisi.

ADB menyetujui pinjaman senilai $500 juta untuk mendukung transisi energi Indonesia

Ini bertujuan membangun kerangka kebijakan yang kokoh dalam mendukung peralihan menuju energi bersih.

Avaada meningkatkan beban energi terbarukan untuk penuhi permintaan pusat data India

Perusahaan menargetkan kapasitas energi terbarukan sebesar 30 gigawatt pada 2030.

Asia-Pasifik mungkin tidak mencapai target energi terbarukan

Negara-negara di kawasan itu harus menarik investasi untuk memajukan tujuan energi bersih mereka.

Laba bersih Adaro turun 12% menjadi $880 juta di Semester 1

Pendapatan turun 15% menjadi $2,97 miliar pada periode tersebut.

ACEN dan Barito Renewables bermitra untuk mempercepat energi angin di Indonesia

Kemitraan ini akan dijalankan oleh anak perusahaan mereka.

Malaysia diminta mengintegrasikan jaringan listrik untuk mempercepat pertumbuhan tenaga surya

Pembatasan penetrasi tenaga surya ke jaringan pada 24% dari permintaan puncak dapat menghambat ekspansi.