Unresolved contractual issues hamper progress of Parbati-II HEP works

The pending resolution of contractual issues has led to severe time and cost overruns for completion of work related to the head race tunnel (HRT) and other critical activities at NHPC's Parbati-II hydro electric project (HEP). More delays are now expected since no solution seems to be in sight, despite numerous negotiations held between the state-owned equipment major, BHEL and NHPC.

No progress on HRT overt lining works in August has forced NHPC to carry forward the balance quantity to be finished in the coming month. Barely half of the lining has been laid out during the month, with 16,012 m of overt lining still remaining to be completed for the project. Moreover, 4,915 m of HRT needs to be excavated as per schedule to avoid any further delay in project commissioning.

Also, in the sphere of electro mechanical (E&M) works, the power house (PH) activities were suspended due to slide of backhill slope. Although the work has resumed, the progress is not up to the mark for the project.

In contrast to this, the retendering of Manihar Pancha and Jiwa Nallah feeder tunnels has progressed smoothly. With the excavation done so far, 59 m and 1291 m for the two tunnels respectively, remains to be completed.

Parbati-II HEP, in the state of Himachal Pradesh, entails the construction of a 85 m high, concrete gravity dam, a 6 m x 31.52 km Head Race Tunnel, a 17 m x 130 m surge shaft, 2 m x 3.5m x 2133 m pilot shaft, a surface power house, pelton turbine and a 400 kV switchyard.


 

Jaringan listrik lemah Vietnam menghambat kebijakan pembelian listrik yang langsung

Infrastruktur energi yang buruk menghambat integrasi kapasitas baru dari proyek energi terbarukan (EBT).

Penutupan pembangkit listrik batu bara baru di ASEAN pada 2040 mungkin tercapai

Penambahan pembangkit batu bara baru dan retrofit pembangkit yang ada menjadi risiko lebih besar dalam transisi.

ADB menyetujui pinjaman senilai $500 juta untuk mendukung transisi energi Indonesia

Ini bertujuan membangun kerangka kebijakan yang kokoh dalam mendukung peralihan menuju energi bersih.

Avaada meningkatkan beban energi terbarukan untuk penuhi permintaan pusat data India

Perusahaan menargetkan kapasitas energi terbarukan sebesar 30 gigawatt pada 2030.

Asia-Pasifik mungkin tidak mencapai target energi terbarukan

Negara-negara di kawasan itu harus menarik investasi untuk memajukan tujuan energi bersih mereka.

Laba bersih Adaro turun 12% menjadi $880 juta di Semester 1

Pendapatan turun 15% menjadi $2,97 miliar pada periode tersebut.

ACEN dan Barito Renewables bermitra untuk mempercepat energi angin di Indonesia

Kemitraan ini akan dijalankan oleh anak perusahaan mereka.

Malaysia diminta mengintegrasikan jaringan listrik untuk mempercepat pertumbuhan tenaga surya

Pembatasan penetrasi tenaga surya ke jaringan pada 24% dari permintaan puncak dapat menghambat ekspansi.