What are the woes in Myanmar's energy mix?

No new MOA or PPA has yet to be concluded for two years already.

It has already been two years since Myanmar’s newly democratised government came to political power, but much to the frustration of energy firms, a new MOA or PPA has yet to be concluded to increase another kind of power in the country: electrical power.

As OWL Energy’s Greater Mekong manager Jeff Miller put it, “Nothing has been signed since democracy came.”

For the past 17 years, Myanmar’s electricity demand has more than doubled mostly due to hydropower, said IHS Markit senior research analyst Joo Yeow Lee. Installed hydropower capacity has grown five-fold since 2000 to 3,000MW in 2017. “However, this puts the system at risk to seasonal swings,” he added.

Moreover, development has been met with strong public objections due to the displacement of communities, as well as the impact on livelihood and the environment.

Can it meet targets?
Myanmar has set its electrification target to 100%, and so far, it has reached 37% (one of the lowest in Southeast Asia), slightly higher from 30% in 2016. It currently has 5GW of installed capacity, mainly composed of hydropower and gas.

According to Lee, capacity is set to grow as demand has risen from over 6TWh in 2010 to almost 16TWh in 2016, setting the yearly rate at 10%.

Lee is excited over Myanmar’s gas sector as four notices to proceed (NTP) - the equivalent of MOUs in other countries - have been issued to fast-track development of plants with total capacity of 3,111MW. As of 2016, the total capacity of gas has reached 1,824MW.

Young government’s policy woes
However, Miller said that this also raises questions about where the power will be sent. He added that these gas to power projects are far from where most the consumers are. “It’s going to need transmission lines as well,” he said.

“Gas and power plants are not fully operated due to poor maintenance,” he added. Reserves will also need five to 10 years to develop. “LNG is a short-term option, but gas laws need updating.”

There are also no policies to incentivise renewables. According to a note by Edwin Vanderbruggen of VDB Loi, the government is also still confused in implementing a furnished approval process, whilst NTPs can only serve to fast-track the completion of deals.

“A lack of experience on the government side, and I suppose a lack of familiarity with Myanmar on the sponsor side, is a commonly held notion to explain the slow progress,” he said. 

Jaringan listrik lemah Vietnam menghambat kebijakan pembelian listrik yang langsung

Infrastruktur energi yang buruk menghambat integrasi kapasitas baru dari proyek energi terbarukan (EBT).

Penutupan pembangkit listrik batu bara baru di ASEAN pada 2040 mungkin tercapai

Penambahan pembangkit batu bara baru dan retrofit pembangkit yang ada menjadi risiko lebih besar dalam transisi.

ADB menyetujui pinjaman senilai $500 juta untuk mendukung transisi energi Indonesia

Ini bertujuan membangun kerangka kebijakan yang kokoh dalam mendukung peralihan menuju energi bersih.

Avaada meningkatkan beban energi terbarukan untuk penuhi permintaan pusat data India

Perusahaan menargetkan kapasitas energi terbarukan sebesar 30 gigawatt pada 2030.

Asia-Pasifik mungkin tidak mencapai target energi terbarukan

Negara-negara di kawasan itu harus menarik investasi untuk memajukan tujuan energi bersih mereka.

Laba bersih Adaro turun 12% menjadi $880 juta di Semester 1

Pendapatan turun 15% menjadi $2,97 miliar pada periode tersebut.

ACEN dan Barito Renewables bermitra untuk mempercepat energi angin di Indonesia

Kemitraan ini akan dijalankan oleh anak perusahaan mereka.

Malaysia diminta mengintegrasikan jaringan listrik untuk mempercepat pertumbuhan tenaga surya

Pembatasan penetrasi tenaga surya ke jaringan pada 24% dari permintaan puncak dapat menghambat ekspansi.